Telangana High Court Rejects Margadarsi Plea Against Rs 81.12 Lakh Electricity Surcharge

The Telangana High Court has dismissed a writ petition filed by Margadarsi Chit Fund Private Limited challenging an electricity surcharge demand of Rs 81.12 lakh relating to power purchased from a private generating company between 2005 and 2015.

Telangana High Court Rejects Margadarsi Plea Against Rs 81.12 Lakh Electricity Surcharge
TTV News

In 30 seconds

  • The case concerned a demand raised by the Southern Power Distribution Company of Telangana Limited (TSSPDCL) on January 31, 2025, seeking Rs 81,12,110 towards Cross Subsidy Surcharge (CSS) for the financial years 2005-06 to 2014-15.
  • The company also relied on the Electricity (Removal of Difficulties) Second Order, 2005, arguing that consumers procuring electricity through such arrangements were exempt from paying CSS.
  • The distribution company argued that the government orders cited by Margadarsi only provided incentives for non-conventional energy generation and did not constitute the specific consent required under Section 43-A(1)(c) of the 1948 Act.

Justice Nagesh Bheemapaka held that government orders issued in 1997 and 1998, which allowed non-conventional energy generators to sell electricity to third parties, did not amount to the specific State Government consent required under Section 43-A(1)(c) of the Electricity (Supply) Act, 1948.

The case concerned a demand raised by the Southern Power Distribution Company of Telangana Limited (TSSPDCL) on January 31, 2025, seeking Rs 81,12,110 towards Cross Subsidy Surcharge (CSS) for the financial years 2005-06 to 2014-15. The demand was subsequently upheld through a speaking order dated June 18, 2025.

Senior counsel K Gopal Chowdary, representing Margadarsi, argued that the company had purchased electricity from M/s Sudha Agro and Chemical Industries Limited, which was authorised to supply power to third parties under the earlier regulatory framework.

The company also relied on the Electricity (Removal of Difficulties) Second Order, 2005, arguing that consumers procuring electricity through such arrangements were exempt from paying CSS.

The distribution company argued that the government orders cited by Margadarsi only provided incentives for non-conventional energy generation and did not constitute the specific consent required under Section 43-A(1)(c) of the 1948 Act.

Accepting the respondents' argument, the High Court observed that Margadarsi had failed to establish that its power generator had obtained the required consent from the State Government.

The Court also noted that the company had not produced evidence of such consent before the relevant authorities or during the High Court proceedings.

Finding insufficient grounds to grant the requested relief, the Court dismissed Margadarsi's writ petition, leaving the Rs 81.12 lakh surcharge demand unchallenged by this petition.