Nagarjuna Sagar Row: Telangana Engineers Question Action Over Palnadu Project

Officials face notices despite ministerial claims that the state had prior knowledge of works

Nagarjuna Sagar Row: Telangana Engineers Question Action Over Palnadu Project
TTV News

In 30 seconds

  • Telangana Irrigation Department issued notices to engineers and the Nalgonda Collector
  • Notices question why officials failed to flag the Palnadu Water Grid project
  • Andhra Pradesh is constructing three intake wells at Nagarjuna Sagar right bank
  • The project aims to draw one point eight six TMC drinking water
  • Field engineers oppose the notices, citing minister statements claiming prior state awareness
  • Irrigation Minister N Uttam Kumar Reddy claimed the issue was raised earlier
  • Minister Komatireddy Venkat Reddy stated officials were reprimanded for reporting failures
  • Andhra Pradesh floated tenders in January and started preliminary work in March
  • Telangana lodged a formal objection with KRMB only on November 16
  • Construction reached twenty percent before the state formally approached the river board

The Telangana government's decision to hold Nagarjuna Sagar irrigation engineers accountable for not flagging Andhra Pradesh's Palnadu Water Grid project has sparked controversy, with departmental staff questioning the administration's stance.

The Irrigation Department issued notices seeking explanations from officials at the Superintending Engineer, Executive Engineer, Deputy Executive Engineer, and Assistant Engineer levels. They were questioned for allegedly failing to alert the state about the construction of three intake wells and related works. The government also sought an explanation from the Nalgonda District Collector.

Reports from the Collector and the Nagarjuna Sagar Chief Engineer have been submitted to the administration, and action appears likely against at least two officials. However, departmental engineers are strongly opposed to any disciplinary steps, arguing that field staff are being unfairly targeted.

Engineers pointed out that Irrigation Minister N Uttam Kumar Reddy had publicly claimed the state was already aware of the works and had taken up the matter with the Union Jal Shakti Ministry, the Krishna River Management Board, and the Andhra Pradesh government. If the administration had prior knowledge, engineers asked why local field officers were now being held liable for an alleged lack of communication.

Conflicting accounts between cabinet colleagues have intensified scrutiny. While the Irrigation Minister maintained that the government tracked the project and raised objections with relevant authorities, Roads and Buildings Minister Komatireddy Venkat Reddy stated that he had reprimanded officials for failing to bring the project to the government's notice.

Project records show Andhra Pradesh invited tenders in January and released a Government Order on August 4. Preliminary survey work began in March. The 1,200-crore rupee project involves three intake wells on the right bank of Nagarjuna Sagar and 200 tanks to draw 1.86 TMC of water for Palnadu district, funded jointly by the Centre and Andhra Pradesh under Jal Jeevan Mission 2.0.

Nearly twenty percent of the construction was completed before Telangana lodged a formal protest with the river board on November 16. The state government has not made the contents of that letter public, and the issue was not placed on the agenda for earlier board meetings.